QUICK ANSWER

Rig-up is the sequence that turns delivered iron into a working treating line: unload and check the pieces, lay out the line in flow order, make up the unions section by section, then pressure test the assembled line before the first stage. The order matters because each step protects the next one — a damaged union caught at the truck is a quick swap, while the same union found during a pressure test is a delay. A good rig-up is not fast for its own sake; it is methodical, with every joint checked, every valve cycled, and the line tested before pressure goes in.

01

Delivery and the first check

Rig-up starts before any iron is laid on the ground. When the truck arrives, the first job is to check what was delivered against the line list: count the pieces, confirm the lengths, sizes, and union figures, and match the drawing numbers to the order. A pup joint in the wrong length or a swivel in the wrong style is a small problem at the truck and a large one once the line is half built.

While the iron comes off the truck, look at each piece. Check union ends and sealing surfaces for dents, scoring, or grit picked up in transit, confirm caps are still in place, and set aside anything damaged rather than letting it reach the line. Stage the pieces near where they will be used — pump discharge iron by the pumps, manifold iron by the manifold, pup joints and spares where the crew can reach them — so nobody is carrying iron across the location during make-up.

02

Spotting equipment and laying out the line

With the iron checked, the spread is spotted: pumps, manifold, and the wellhead connection take their positions first, because the treating line has to connect them. Laying the line out in flow order — pump discharge, manifold, main treating line, wellhead connection — keeps the build simple and makes every section easy to find and inspect.

Leave working clearance around the line. Crews need room to swing a hammer on the unions, walk the iron during the pressure test, and reach every valve without climbing over equipment. Plan where restraints will go as the line is laid out, not after it is made up, and leave the final make-up points accessible so a pup joint can be swapped if the measurement changes. The longest runs go down first; pup joints in 4 ft, 6 ft, and 10 ft close the measured gaps last, so the line is not forced together.

03

Making up the line, section by section

  • Match at every make-up: nominal size, union figure, and male and female orientation must agree across the joint. A mismatched figure will not seal, and forcing it only damages the union.
  • Inspect before you tighten: look at the sealing surfaces and union faces as each joint is made up. A dent or a piece of grit caught in the seal is the most common reason a union weeps on the first test.
  • Tighten unions the way the procedure calls for: hammer unions are made up with the hammer and checked for a firm, even seat — snug is not the same as sealed, and over-tightening damages the threads.
  • Cycle every plug valve through its full travel before the line is tested, and confirm it moves smoothly with a positive stop. A valve that is stiff or will not seat on the ground will not improve under pressure.
  • Align swivels with the route: a Style 10 or Style 50 swivel should sit naturally in the line without side loading, and should turn freely by hand through its range. A swivel that binds or has side play is a sign to set it aside.
  • Support and restrain as you go: the finished line should be supported, with restraints placed under the site procedure, and every union left accessible for inspection before the job and for safe break-out after it.
04

Testing before the first stage

No line goes to the first stage without a pressure test. The assembled line is isolated, filled with the test medium the procedure specifies, vented of air, and brought up to the test pressure gradually, then held for the period the procedure requires while the crew watches the gauges and walks the line looking for leaks, weeping unions, or pressure drop. Everyone not needed for the test stays clear of the pressurized line.

If a union weeps, the pressure is bled off before anything is touched — never tightened or adjusted under pressure — and the test is repeated after the fix. A passed test is recorded against the line, with the date, the test pressure, and who performed it, so the first stage starts with a record, not a memory. That record is also what the next rig-up starts from: which lengths and styles were used, and where, so the crew is not guessing again next time.

05

Where Sterling can help

Sterling Wellhead stocks new 2-inch FIG 1502, 10,000 PSI flow iron in Jourdanton, Texas 78026, including the T000856 plug valve, 4 ft, 6 ft, and 10 ft pup joints (T000864, T000866, T000855), and Style 10 and Style 50 swivel joints (T000620, T000693). Send the line list, the quantities and drawing numbers, the delivery location, and the required-on-site date, and ask for the pressure test documentation with your RFQ — our team will confirm the configuration by drawing number. Sterling is RFQ-only: contact sales@sterlingwellhead.com or +1 (512) 373-0384.

FAQ

Frequently asked questions

How long does a rig-up usually take?+

It depends on the size of the spread, the length of the line, and the crew's experience — a short flowback line can be rigged up in hours, while a large frac spread takes longer. What matters is not the clock but the sequence: checking at delivery, laying out in flow order, making up section by section, and testing before the first stage. Skipping a step to save time is usually what causes the delay.

What should be checked when flow iron is delivered?+

Count the pieces against the line list, confirm lengths, sizes, union figures, and drawing numbers, and inspect union ends and sealing surfaces for transport damage. Confirm caps are in place, the pieces are dry inside, and the pressure test records for the iron are current for the job it is going to.

Why pressure test the assembled line if each piece was already tested?+

Individual tests prove the pieces; the assembled-line test proves the make-ups, the layout, and the line as a system. A joint that passed on its own can still weep at a union that was made up with grit in the seal or a figure that does not match. The assembled test is the last check before the first stage, and the one that catches those problems.